Eccles Place, Dublin 1
A request has been received from Kavanagh Crane Hire for the following temporary road closures:
- Location: Eccles Place ( From Dorset Street to Leo Street )
- Period: Saturday 18th February 2012
- Times: 08.30 to 16.30hrs inclusive
The temporary road closure is to facilitate a crane lift.
Traffic Management Plan
- Westbound traffic from Dorset Street Lower to Eccles Place will be diverted via Dorset Street Lower, Synnott Place, St.Josephs Street and Leo Street.
- Pedestrian and local access will be maintained.
Grangegorman Road Upper, Dublin 7
A request has been received from Dublin City Council’s Drainage Division for the temporary road closure of the following road:
- Location: Grangegorman Road Upper (Rathdown Road to North Circular Road)
- Period : From Monday 13th February to Monday 27th February 2012
- Times: 10.00am to 04.00pm each day.
The road closure is to facilitate drainage reconstruction works.
Traffic Management Plan
- Traffic on North Circular Road wishing to travel on Grangegorman Road Upper to Grangegorman Road Lower will be diverted via Rathdown Road.
- Traffic on Grangegorman Road Lower wishing to travel on Grangegorman Road Upper to North Circular Road will be diverted via Rathdown Road.
- Pedestrian and local access will be maintained.
John’s Lane West,Dublin 2
Pierce Healy Developments intend to close the following road on the date and times stated below:
- Location John’s Lane West
- Period: Monday 30th January to Friday 03rd February 2012 and Thursday 01st March 2012
- Times: 00.00hrs to 24.00hrs inclusive
The temporary road closure is to facilitate crane lifting operations.
Traffic Management Plan
- Traffic on Thomas Street wishing to enter John’s Lane West will be diverted via John Street West.
- Local vehicular access will be maintained from John Street West.
- Pedestrian access will be maintained.
Johns Lane West (from Thomas Street to John Street West)
Pierce Healy Developments intend to close the following road on the date and times stated below:
- Location: John’s Lane West
- Period: Monday 23rd January to Friday 27th January 2012 and Monday 13th February to Friday 17th February 2012
- Times: 00.00hrs to 24.00hrs inclusive
The temporary road closure is to facilitate crane lifting operations.
Traffic Management Plan
- Traffic on Thomas Street wishing to enter John’s Lane West will be diverted via John Street West.
- Local vehicular access will be maintained from John Street West.
- Pedestrian access will be maintained.
Bow Street, Dublin 7
Dublin City Council’s Road Construction Division intends to close the following road on the dates and times as stated:
- Location: Bow Street (New Church Street to Hammond Lane including LUAS crossing)
- Period: From 0.00hrs on Monday 06th February to 24.00hrs on Friday 16th March 2012.
The road closure is to facilitate road reconstruction works.
Traffic Management Plan
- Traffic on Lincoln Lane / Hammond Lane / Phoenix Street wishing to travel on Bow Street across Luas track to North King Street will be diverted via Stable Lane, Arran Street, Arran Quay, Church Street and May Lane.
- Traffic on Bow Street wishing to cross Luas track to Lincoln Lane / Hammond Lane / Phoenix Street will be diverted via New Church Street and Arran Street.
- Pedestrian and local access will be maintained.
Cumberland Court and Westmoreland Court, Dublin 2
ESB Networks intends to close the following roads on the dates as stated:
Location: Cumberland Court and Westland Court, Dublin 2
Period: Tuesday 7th June 2011 to Wednesday 6th June 2012
Time: Entire Period
The temporary road closure is to facilitate construction of new ESB sub-station.
Traffic Management Plan
- Cumberland Court will be closed to vehicles for the duration of the works
- Limited vehicular access will be maintained on Westland Court