Moore Lane (from Parnell Street to O’Rahilly Parade), Dublin 1

Printer-friendly version

Sheahan & Collins Construction intends to close the following road to facilitate development site concrete delivery operations on the dates and times listed below:

Moore Lane (from Parnell Street to O’Rahilly Parade), Dublin 1

From 08.00 hrs. to 14.00 hrs. per Thursday:

Period 1:          19/03/2020      Period 15:       25/06/2020      Period 29:       01/10/2020

Period 2:          26/03/2020      Period 16:       02/07/2020      Period 30:       08/10/2020

Period 3:          02/04/2020      Period 17:       09/07/2020:     Period 31:       15/10/2020

Period 4:          09/04/2020      Period 18:       16/07/2020:     Period 32:       22/10/2020

Period 5:          16/04/2020      Period 19:       23/07/2020:     Period 33:       29/10/2020

Period 6:          23/04/2020      Period 20:       30/07/2020:     Period 34:       05/11/2020

Period 7:          30/04/2020      Period 21:       06/08/2020:     Period 35:       12/11/2020

Period 8:          07/05/2020      Period 22:       13/08/2020:     Period 36:       19/11/2020

Period 9:          14/05/2020      Period 23:       20/08/2020:     Period 37:       26/11/2020

Period 10:        21/05/2020      Period 24:       27/08/2020:     Period 38:       03/12/2020

Period 11:        28/05/2020      Period 25:       03/09/2020:     Period 39:       10/12/2020

Period 12:        04/06/2020      Period 26:       10/09/2020:     Period 40:       17/12/2020

Period 13:       11/06/2020      Period 27:       17/09/2020:    

Period 14:       18/06/2020      Period 28:       24/09/2020:   

Traffic Management Plan

  • Traffic on Parnell Street wishing to travel on Moore Lane will be diverted via Moore Street and O’Rahilly Parade.
  • Traffic on Moore Lane wishing to travel on Parnell Street will be diverted via O’Rahilly Parade and Moore Street.
  • Pedestrian and local access will be maintained.