Moore Lane (from Parnell Street to O’Rahilly Parade), Dublin 1

Printer-friendly version

Sheahan & Collins Construction, Block B, Maynooth Business Park, Co. Kildare W23 W5X7 intends to close the following road to facilitate development site concrete delivery operations on the dates and times listed below:

Moore Lane (from Parnell Street to O’Rahilly Parade), Dublin 1

  • Period 1:          From 07.00hrs to 14.00hrs on Thursday 6th February 2020.
  • Period 2:          From 07.00hrs to 14.00hrs on Thursday 13th February 2020.
  • Period 3:          From 07.00hrs to 14.00hrs on Thursday 20th February 2020.
  • Period 4:          From 07.00hrs to 14.00hrs on Thursday 27th February 2020.
  • Period 5:          From 07.00hrs to 14.00hrs on Thursday 5th March 2020.
  • Period 6:          From 07.00hrs to 14.00hrs on Thursday 12th March 2020.

Traffic Management Plan

  • Traffic on Parnell Street wishing to travel on Moore Lane will be diverted via Moore Street and O’Rahilly Parade.
  • Traffic on Moore Lane wishing to travel on Parnell Street will be diverted via O’Rahilly Parade and Moore Street.
  • Pedestrian and local access will be maintained.

 