Roadworks and Construction Updates

Learn about planned roadworks and traffic management arrangements for the Beatty’s Avenue to Herbert Park section of The Dodder Greenway.

Construction Update 12/08/2025

There are construction roadworks planned for Saturday 16 August from 9am, on Anglesea Road near the junction with Merrion Road. Please find TMPs attached below.

Summary:

  • The southbound lane on Anglesea Road (towards Donnybrook) will be closed.
  • Anglesea Road will not be accessible from Merrion Rd. A diversion will be in place via Simmonscourt Road to ensure access is maintained during the works.
  • The right turn traffic light and the left turn slip lane to Anglesea Road from Merrion Road, will both be closed during the works.
  • One inbound lane on Merrion Road will be closed (for approx. 100m) at the junction with Anglesea Road.
  • The northbound lane on Anglesea Road (towards Ballsbridge) including the left turn on to Merrion Road will not be affected.
  • Apart from the right turn filter on Merrion Road, traffic lights will not be affected
  • Local stakeholders have been made aware of the works.
  • Pedestrian access will be maintained at all.
9170-R815 Anglesea Road Ballsbridge Dublin tmp 017
9170-R815 Anglesea Road Ballsbridge Dublin tmp 033

Construction Update 25/07/2025

There are construction roadworks planned for Sat 26th July from 9am, on Anglesea Rd. Please find TMP attached.

Summary:

  • There will be stop and go traffic management outside the entrance to the Herbert Park Hotel for northbound and southbound traffic on Anglesea Rd.
  • Traffic on Merrion Rd will not be affected.
  • Traffic lights will not be affected.
  • Local stakeholders have been made aware of the works.
  • Pedestrian access will be maintained at all times.
9170-R815 Anglesea Road Ballsbridge Dublin tmp 017

Construction Update 27/06/2025

There are construction roadworks planned for tomorrow Sat 26th June 9am until that evening, at the intersection of Merrion Rd and Anglesea Rd. Please find TMPs attached.

Summary:

  • The inbound traffic will be reduced to one lane on Merrion Rd for 100m at either side of the junction of Anglesea Rd (200m total).
  • Outbound traffic on Merrion Rd will not be affected.
  • The northbound lane of Anglesea Rd will be closed between Simmonscourt Rd and Merrion Rd. Northbound traffic on Anglesea Rd (coming from Donnybrook direction) will access Merrion Rd via Simmonscourt Rd (as per TMP-030).
  • Southbound traffic on Anglesea Rd will be as normal.
  • Traffic lights will not be affected.
  • Local stakeholders have been made aware of the works.
  • Pedestrian access will be maintained at all times.
9170-R815 Anglesea Rd Ballsbridge Dublin-TMP-026_REV_01
9170-R815, Anglesea Rd, Ballsbridge, Dublin-TMP-004
9170-R815, Anglesea Rd, Ballsbridge, Dublin-TMP-030
Contact Details