Current Roadworks Burlington Road, Dublin 4 Period 1

Kavanagh Crane Hire Ltd intends to close the following road to facilitate replace chiller unit on roof on the dates and times listed below:

Location

Burlington Road, Dublin 4

Time

From 08.00hrs to 20.00hrs

Date

Sunday 28th June 2026.

Traffic Management Plan

  • Pedestrian access will be facilitated at all times.
  • Local access will be facilitated when possible, from all closure points.
  • Traffic Marshalls to manage closure points during works.
  • Traffic arriving from Mespil Road will be diverted to Baggot Street Upper – Waterloo Road.
  • Traffic arriving from Burlington Road will be diverted to Burlington Road – Waterloo Road – Baggot Street Upper – Mespil Road.