Royal Canal Greenway: From North Strand Road to Phibsborough Road
The Royal Canal Greenway Phase 3 (RCGP3) will provide segregated walking and cycling facilities along a 2.1km route that extends from North Strand Road (Newcomen Bridge), along the banks of the Royal Canal to Phibsborough Road (Cross Guns Bridge). The route is identified as a primary greenway route in the Greater Dublin Area Cycle Network Plan, published by the National Transport Authority in 2013.
Timeline
Q4 2015
Part 8 Approved
Q2 2022
Tenders advertised
Q1 2023
Construction Start
Q2 2025
Construction complete

Project Overview
Project Overview
Overview of the project
How to contact us

Maps & Reports
Maps & Reports
Presentation to Local Area Committee
General Arrangement drawings
Landscaping drawings
Business Plan
Scheme visualisations/rendered drawings

FAQs and Information Leaflets
FAQs and Information Leaflets
Project Information

Construction Updates & Notifications
Construction Updates & Notifications
Construction updates throughout the project

Royal Canal Towpath at Binns Bridge – Part 8
Royal Canal Towpath at Binns Bridge – Part 8
Information about Part 8 Public Consultation (10 July – 23 August 2023)