Royal Canal Greenway – Phase 3

To view this, you must update your

The Royal Canal Greenway Phase 3 (RCGP3) will provide segregated walking and cycling facilities along a 2.1km route that extends from North Strand Road (Newcomen Bridge), along the banks of the Royal Canal,”  along the banks of the Royal Canal to Phibsborough Road (Cross Guns Bridge). The route is identified as a primary greenway route in the Greater Dublin Area Cycle Network Plan, published by the National Transport Authority in 2013.

Timeline

Q4 2015

Part 8 Approved

Q2 2022

Tenders advertised

Q1 2023

Construction Start

Q2 2025

Construction complete