C2CC Project: Construction Works
The project will be completed in seven sections, as follows:
- Section 1 – Talbot Street to Buckingham Street.
- Section 2 – Buckingham Street to the Five Lamps Junction at Portland Row.
- Section 3 – Five Lamps Junction to Annesley Place.
- Section 4 – Annesley Place to Poplar Row.
- Section 5 – Poplar Row to Fairview Strand.
- Section 6 – Fairview Strand to Malahide Road.
- Section 7 – Malahide Road to Alfie Byrne Road.
Construction works have now commenced on all inbound sections.
Construction works are also underway on outbound section 2 and outbound section 7.
For further information about existing traffic management activities, please see here.
Access to Premises:
Pedestrian access to premises along the project route will be maintained at all times during the works. When excavating the road outside individual premises, vehicular access may necessarily be temporarily interrupted. The contractor will liaise with those affected in advance of the work to minimise disruption.
Similarly, access for emergency services, and refuse collection, will also be maintained.
Acknowledgement:
Dublin City Council apologises for any inconvenience caused and seeks the public’s understanding and co-operation during the course of these works.
Contractor Details:
In January 2022, Dublin City Council awarded the contract for construction of the Clontarf to City Centre Project to Clonmel Enterprises Ltd.
The contact details for the main contractor for the works are:
Clonmel Enterprises Limited
24-Hour Emergency Contact: 086 032 4904
Email: [email protected]
Web: http://www.clonmelent.com