12/02/2024- Works to take place between The East Point Business Park on Alfie Byrne Road and the Junction of East Road on East Wall Road
Resurfacing works will begin next Monday evening the 19th of February on the East Coast trail. Works will be carried out over a 3 week period and will take place between The East Point Business Park on Alfie Byrne Road and the Junction of East Road on East Wall Road. Please see below sketch
8/1/2024 - Closure of left-hand inbound lane on Alfie Byrne and East Wall Road.
Monday 8th of Jan – Works will begin on the islands at the corner of the East Wall Rd and Alfie Byrne Road Jct – This will see the full left hand lane from East point Business Park to the East Wall Rd junction Closed.
Tuesday 9th of Jan – the remaining left hand lane from the ABR/East Wall Rd junction to Church road will be closed to facilitate the construction of the new traffic islands at the Church Road Junction.